It’s almost a year from the kick off meeting to implement ERP and MES project, VMD and ITG held a meeting to evaluate the project’s outcome at VMD Head quarter. It gives us great pleasure to annouce that the ERP has reached the point where all critical processes are now go LIVE and providing excellent business support.
The MES is currently undergoing UAT and will be operational by the end of June. It will assist our factory in controlling production planning, WIP control, and facility maintenance once it is ready to use.
Thank you to the VMD team for working relentlessly to ensure the success of this project, as well as to ITG for their expert assistance with the current project.